| |
THE WEST SOMERSET RAILWAY
A Description of the Signalling by Kevin Weston
Bishops Lydeard

Bishops Lydeard is the latest signalling project on the railway.
The exact opening date of the signal box is unclear; three sources give the
dates of 1902, 1904 and 1906. It is not known what signalling, if any, existed
before these dates. The first frame had 25 levers with Stud locking and
controlled a layout that consisted of a crossing loop, two sidings located
behind the signal box and a third siding to a goods shed opposite, which is now
used as a museum. In 1934, when the line from Norton Fitzwarren was doubled, a
new 33-lever frame with tappet locking was installed. This was in use until
1970 when the signal box closed and the line was singled. BR removed all
equipment from the signal box but left most of the track in place, all points
were secured with clips. When the WSR resumed operations, the station was to be
the southern terminus of passenger services. With the limited traffic at the
time, One Train Working was used with a wooden train staff. To run-round
trains, there had to be some alterations to the track at the south end and the
Railway Inspectorate required that the points at each end of the platforms were
connected to ground frames which were interlocked by the train staff. This
system operated for many years, although as the traffic increased, the working
of extra trains was restricted. To overcome this, it was decided to operate the
station as a block post with Train Staff and Ticket to Williton on busy days.
This provided the limited flexibility to allow a second train in the same
direction after the first train had cleared the section.
In 1981, plans were drawn up for new signalling scheme. A new
frame of 33 levers was installed, using part of the frame recovered from
Westbury South, however, for various reasons, not least cost, the scheme was
not completed. In 1994/5, the loop was extended to its present length of 275
yards. Once Crowcombe was opened, there was a greater necessity for signalling
to make full use of the shorter block sections. In 1997 plans were drawn up for
submission to the Railway Inspectorate. The station was still operated as a
terminus so we had to allow for trains to arrive and depart from either
platform; allowance was also made for through trains from Railtrack. Semaphore
signals are used throughout except on the Norton section where there are to be
colour light signals. The frame installed in 1981 was re-locked to operate the
new layout; the colour light signals are to be operated by switches.
Installation will be in two stages, the north end was brought into use between
4th and 11th August 1998 and consisted of one point, four single arm stop
signals, a four-arm bracket signal and a new distant signal. The bracket signal
has a stop arm and a calling-on arm for entry to each platform. The home signal
for trains from Crowcombe is the third on the railway to be worked by a
Westinghouse signal motor. A Westinghouse style M3A point machine, the same
type as used at Blue Anchor, operates the point. Six track circuits are
provided as the approach to the station is out of sight of the signal box. This
is the first signal box on the railway where we have used BR specification
50-volt plug-in relays for the main interlocking. The older 12-volt shelf
relays are no longer available in large numbers so we have to upgrade to the
modern standard.
We suffered a few set backs
early in the scheme, woodworm and dry rot were found in the signal box floor
and some of the support timbers. The tiles on the roof where found to be loose
and a number of them had to be replaced. This delayed the re-locking of the
frame and the installation of the new wiring. We also suffered from a number of
thefts. Most of the items taken appeared to be for collectors,
these included a reconditioned ground signal. The signal did not have a lamp
case attached so the thieves returned two days later to Crowcombe and took one
from a working signal. We also lost two new signal arms and about £7000
worth of signalling cable in three separate occasions. One of the most unusual
items taken was a number of track circuit bonds, these are lengths of
galvanised steel wire that go across the rail joints in track circuits. They
have no real scrap valve, and certainly no valve to a collector,
but an unopened 25-kg bundle was taken.
Work on the south end will involve removing the south ground frame
and connecting the points to the signal box. Five runs of between 100 yards and
200 yards are required, a total of 900 yards of rodding. The goods shed points
are clipped out of use at the moment, but these should be first to be connected
the signal box as stage 2a. Two more bracket signals are to be erected; the
first was raised on Wednesday 12th April. There is also a centre-balanced
wooden signal arm, this is all new as the original arm had rotted and there was
rust in the metal frame. Most of the south end signalling has been installed,
throughout the summer it will be connected up and tested. Even after testing we
must wait for permission from the Railway Inspectorate before it can be brought
into use.
|